| 1. Turn back the specified
amount of rope from the thimble. Apply the first clip one base
width from the dead end of the wire rope (U-bolt over dead end
-- live end rests in clip saddle). Tighten nuts evenly to recommend
torque. |
1. Turn back the specified
amount of rope from the thimble. Apply the first clip one base
width from the dead end of the wire rope. Tighten nuts evenly
to recommended torque. |
| 2. Apply the next clip as
near the loop as possible. Turn on nuts firm but do not tighten. |
2.Apply the next clip as
near the loop as possible. Turn on nuts firm but do not tighten. |
| 3. Space additional
clips if required equally between the first two. Turn on nuts
-- take up rope slack -- tighten all nuts evenly on all clips
to be recommended torque. |
3. Space additional
clips if required equally between the first two. Turn on nuts
-- take up rope slack -- tighten all nuts evenly on all clips
to recommended torque. |
| 4. NOTICE! Apply
the initial load and retighten nuts to the recommended torque.
Rope will stretch and shrink in diameter when loads are applied.
Inspect periodically and retighten. |
4. NOTICE! Apply
the initial load and retighten nuts to the recommended torque.
Rope will stretch and shrink in diameter when loads are applied.
Inspect periodically and retighten. |
| IMPORTANT: Failure to make
a termination in accordance with aforementioned instructions,
or failure to periodically check and retighten to the recommended
torque, will cause a reduction in efficiency rating. |
IMPORTANT: Failure to make
a termination in accordance with aforementioned instructions,
or failure to periodically check and retighten to the recommended
torque, will cause a reduction in efficiency rating. |